The City of Mountain Home’s Water Department has been hard at work relocating the water main. They started on East Jackson St. and worked their way up Main St. to East 2nd North. To accommodate the downtown businesses, the Water Department crew adjusted their schedules and started at 5:00 a.m. on Thursday, September 19th to break the line. The crews continued working up Main St. from East 2nd North to American Legion on Monday, Sept. 23.

East Jackson Street to East 2nd North Street -

• Crews will be working diligently to finish their work to get East Jackson reopen. Asphalt crews started on Friday, September 20th patching the trench lines behind the storm drain installation.

• Jackson from Main Street towards the railroad tracks is now open.

• Jackson from Main Street to North 2nd East Street will open this week.

• Storm drain utilities will be headed down Main Street towards East 2nd North Street.

• Once the storm drain is complete on the block of Main Street between East Jackson and North 2nd East Street, demo of the sidewalks will start on September 30th.

East 2nd North Street to American Legion -

• City crews are working on relocating the water mains. Storm drain work will move into the intersection of East 2nd North Street later in this week.

• The intersection of Main Street and East 2nd North Street will remain closed until approximately Friday, September 27th. The alleys will remain open and access from North 2nd East Street onto East 2nd North Street will remain open. Traffic will not be able to turn onto East 2nd North Street from Main Street. This intersection is still anticipated to be open by Friday, September 27th.

American Legion to East 4th North Street -

• Utility work will begin September 30th.

Based on public outreach, a stop sign will be added to our temporary traffic control at the intersection of American Legion and Main Street to help traffic turning onto Main Street. We are grateful for our community providing feedback and solutions to support any issues that may arise. We would be remiss if we did not also thank the Idaho Transportation Department (ITD) for their continued partnership to ensure our community’s safety and mobility during travel. East 4th North Street to East 5th North Street -

• Utility work to begin October 7th.